SURVEY

View our Community Survey Results

Click here

close

Main Streets

We will be posting all of the information we receive on this project here.

 

Click Here to View Details on the Project via City of Calgary Website

 

Click the Link Below to view some condensed facts and information about this project:

MLMS Quick Facts – Oct 2023 – GENERAL

 

Notice – July, 2024

Project update – July 2024

Significant work occurring week of July 22

We know you want construction to be completed as quickly as possible. As such, we’re accelerating our pace in certain areas. But this means multiple streets and sidewalks will be shut down to progress the work. Parking will be limited. We know this is impacts you. We will work hard to get this done safely and efficiently. Thank you for your patience and understanding.

July 22 – August 10 Detours map

  • 36 Avenue at 18 Street through 19 Street
  • Full road closure
  • No parking in the area

July 22 – August 18 Detours map

  • 33 Avenue at 18 Street through 20 Street
  • This is the first of three phases of work; future phases will be communicated
  • Northside road construction – eastbound traffic maintained but 18 Street will be closed to traffic
  • No parking in the area

July 22 – early September Detours map

  • 33 Avenue at 20 Street through 22 Street
  • South side sidewalk construction work will start in areas where the previous north side work has been completed

June 10 – July 16 Detours map

  • 18 Street between 34 and 36 Avenues – Road closed to vehicle access for porous paver installation

July 19 – Night Market detour – Noon – 11 p.m. Detours map

June 28 – July 19 (phase 2/3) Detours map

  • 33 Avenue/20 Street – From Circle K building face to 32 Avenue will be closed. The center median on 20 Street will have been removed with stage 1 construction, this will allow traffic to get in and out of the Circle K entrance/exit.
  • The back lane driveway will remain open for East/West movement (gravel).

July 2 – October 1 – Detours map

  • 34 Avenue west of 22 Street – Sidewalk closed connecting 34 Avenue to 33 Avenue next to Crowchild Trail

July 16 – August 6 – Detours map

  • 36 Avenue/18 – 19 Streets – Road reconstruction

August 6 – October 1 – Detours map

  • 19 Street /34 – 35 Avenues – Road reconstruction

Ongoing construction

  • 36 Avenue between 18 and 19 Street – (8 weeks) no on-street parking, two-way traffic maintained – sidewalk reconstruction.

 

Notice – June, 2024

 

Marda Loop Main Streets

May 31 – Construction Updates

We’re here to answer your questions

 

Have a question or comment? Pop by to chat in person with Dylan, of the Marda Loop Main Streets team.

Community office hours – June

 

When: Wednesdays (June 5, 12, 19, 26) from 9 to 11 a.m.

Where: Phil & Sebastian (2043 33 Ave SW)

 

June 3 – 10

  • 18 St closed at 34 Ave – local traffic access from 36 Ave and 18 St only

 

 

June 5 – 19 (phase one)

  • 33 Avenue/20 Street – Directly North of 33 Avenue to Circle K building face is closed. Also the North half on 33 Avenue from 20 Street West to the Merchants entrance/exit (will remain open)
  • Circle K entrance/exit is closed

 

 

June 10 – July 16

  • 18 St between 34 and 36 Ave – Road closed to vehicle access for porous paver installation

 

 

June 10 – July 7

  • ATCO gas line relocation
  • 33 Ave will be converted to a one-way westbound from 19 to 18 St – at a minimum one lane of westbound traffic will be maintained to ensure a safe working area

 

 

June 26 – July 17 (phase two)

  • 33 Avenue/20 Street – From Circle K building face to 32 Avenue will be closed. The center median on 20 Street will have been removed with stage 1 construction, this will allow traffic to get in and out of the Circle K entrance/exit
  • The back lane driveway will remain open for East/West movement (gravel)

 

 

Ongoing construction

 

  • 18 Street between 34 and 36 Avenues – (8 weeks) parking maintained on the east side, one-way southbound two way local traffic only due to Enmax closure at 18 St – sidewalk reconstruction
  • 36 Avenue between 18 and 19 Street – (8 weeks) no on-street parking, two-way traffic maintained – sidewalk reconstruction
  • 33 Avenue between 22 and 21 Street (April 25 to mid-June) early-July no parking on the north side – sidewalk reconstruction
  • 22 Street north of 33 Avenue to rear lane – vehicle traffic changed to one-way southbound permanently – sidewalk reconstruction

 

Over 190 local businesses open during construction!

The Marda Loop Main Streets project will bring a whole new look to the Marda Loop business district when it is completed in late 2024. Please keep supporting local businesses during the challenges of the construction period – they need you now more than ever!

Support Marda Loop

 

 

For our most up-to-date construction schedule, 

please visit our website.

 

You can always reach the project team at MardaLoopMainStreets@calgary.ca

 

We want to thank the Marda Loop community for its continued support and patience during the engagement, planning and construction processes.

 

Marda Loop Main Streets Project Team

 

 

Notice – March 14, 2023

 

A message from the City and Main Streets Team:

 

Marda Loop Main Streets March Detour Updates:

We have learned of several upcoming detours to support the work of our partners at ATCO and ENMAX. These date estimates are weather dependent, and are outlined in the maps below.

33 Avenue from 19 to 20 Streets S.W. will be a one-way, westbound traffic for the month of March. This is required to support ATCO’s gas line relocation work.·

Northbound traffic will be restricted from 34 Avenue at 19 Street S.W. from March 5 to 13. Local traffic only will be permitted on 19 Street south of 33 Avenue S.W. in support of ENMAX’s underground work.·

The north sidewalk on 36 Avenue east of 19 Street S.W. will be closed March 5 to 14, also in support of ENMAX’s underground work. Flaggers will be onsite to support traffic and pedestrians in the area during the closure.

 

Stay in touch with the project

 

March Office HoursHave a question or comment? Pop by to connect with a member of the Marda Loop Main Streets team in person.

When:
Wednesdays (March 6, 13, 20, 27) from 9 to 11 a.m.
Where:
WOW Bakery (2002 34 Avenue S.W.)

 

For our most up-to-date construction schedule, please visit our website.

You can always reach the project team at MardaLoopMainStreets@calgary.ca.
We want to thank the Marda Loop community for its continued support and patience during the engagement, planning and construction processes.

 

Sign up for the Main Streets emails directly here

 

To support conversations with property owners, businesses, and residents along 34 Avenue S.W., our team has created an animated video.

 

It shows how our work will transform 34 Avenue S.W. this year, highlighting the benefits achieved by reorganizing the road and using the City-owned road-right-of-way. We hope it will help the community visualize the safer sidewalks and intersections, increased connectivity, and new multi-use pathway connected to The City’s Pathway and Bikeway Network (5A). We know retaining on-street parking and two-way traffic is also of importance to the community, so it reiterates that we’re accomplishing both of these goals with the road reorganization

 

 

Notice – November 30, 2023

 

Good news! Two-way traffic will return to 33rd Avenue for the winter starting on Monday, December 4.  Check out the latest update from The Main Streets Team on their web page: calgary.ca/mardaloop.  One-way traffic remains on 34th Avenue to accommodate ongoing utility burial work.

Note: The City sent an email out about this on November 24. if you did not receive it, make sure that you are signed up on the City’s email list to receive info about Main Streets construction sign up here.

 

Tree Removals

 

If you have any questions, please feel free to contact us at MardaLoopMainStreets@Calgary.ca