Hall Revitalization Project
Dear Residents,
We would like to inform you of the upcoming renovation at the Marda Loop Communities Association Hall (3130 16 St SW) taking place this spring and summer season. This work will include repairs to the building exterior, improvements to lighting, updates to gutters and drainage, and upgrades to the entrance canopies.
Prompted by the City of Calgary’s lifecycle planning process, this project will enhance both the safety and visual aspects of the hall. Improvements will include new canopy structures at the upper and lower hall entrances, stucco remediation, updated lighting, replacement of metal sheathing, , new sealants, upgrade of gutters, downspouts and soffit panels.
Construction is scheduled from May to September 2026, with The City of Calgary and approved contractors. During this time, you may experience increased noise and minor traffic disruptions. Project updates and schedules will be shared on our website www.mardaloop.com.
For those with hall bookings and participating in MLCA programs & events, our team will work with you to minimize disruptions and arrange alternatives where needed. We appreciate your patience and support while these improvements are completed. Our goal is to ensure that Marda Loop Communities Association Hall continues to serve as a welcoming and functional space for gatherings for years to come. We look forward to sharing our new look and feel with you this fall!
If you have any questions or would like additional information, please contact Tami Cormack, Director of Sustainability at sustainability@mardaloop.com
Thank you for your continued support of our community.
Sincerely,
Marda Loop Communities Association
Timeline
Phase 1
May 11 – Mid June
Mobilization and Demolition: Work begins with site fencing and layout, followed by the demolition of the canopy, soffit, concrete, and asphalt, as well as stucco remediation.
Phase 2
Mid-June – Mid-July
Earthworks and Foundations: This period focuses on excavations, pouring piles and grade beams, forming pedestals, backfilling, and completing exterior concrete and asphalt work.
Phase 3
Mid-July – Mid-August
Structural Steel and Electrical: Steel erection for the roof and miscellaneous structures takes place in late July, overlapping with the electrical rough-in, which runs from July 30 to August 19
Phase 4
Late August – Late September
Exterior Finishes and Roofing : This stage includes finishing the roof structure, installing soffits, flashing, exterior cladding, new stucco, and exterior lighting
Phase 5
September 23 – September 30
Completion: The final week of the project is reserved for addressing deficiencies, demobilizing from the site, and achieving final completion
Grand Opening Event
October
Stay tuned on news for the unveiling of the new community hall